RC19 Release Board (v0.4.0rc19)

1. Goal

Ship rc19 as a quality-convergence release:

  • close architecture/protocol drift
  • close docs/implementation drift
  • harden quality gates for reproducible releases
  • prepare clean inputs for 0.4.0 GA decision

No large new feature bets in this cycle.

2. Scope Rules

In Scope

  • P0/P1 bug fixes
  • protocol/contract consistency fixes
  • release-critical UX consistency fixes
  • docs truth sync and release assets
  • CI/release gate hardening

Out of Scope

  • major net-new product surfaces
  • speculative refactors without release risk reduction
  • broad compatibility migration projects

3. Full-System Audit Policy

Every tracked file is reviewed through the matrix (docs/release/rc19_file_matrix.csv), with tiered depth:

  • Tier A (deep): per-file + per-public-function audit, design rationale required
  • Tier B (standard): per-file behavior and interface consistency audit
  • Tier C (light): misguidance/staleness/risk-only audit

No file is skipped. Unowned findings are not allowed.

4. Phases and Exit Criteria

R0 Scope Freeze (Day 1)

  • Freeze new feature intake.
  • Create owner map and communication channel.

Exit:

  • scope freeze announced
  • owner map complete

R1 Full Inventory (Day 1)

  • Generate matrix from tracked files.
  • Assign tier, domain, owner, status.

Exit:

  • matrix coverage = 100%
  • all Tier A files have explicit owner

R2 Architecture & Contract Audit (Day 2-3)

  • Audit CCCS, daemon IPC, context ops contracts vs implementation.
  • Audit versioned examples and wire formats.

Exit:

  • contract mismatch list complete
  • all protocol P0/P1 gaps triaged

R3 Runtime Core Audit (Day 3-5)

  • Audit kernel, daemon, delivery, automation, inbox, permission boundaries.
  • Verify state-machine legality and invariants.

Exit:

  • P0 = 0
  • P1 all have owner + fix plan

R4 Port & UX Audit (Day 5-6)

  • Audit CLI/MCP/Web/IM consistency (naming, defaults, behavior).
  • Audit cross-surface terminology consistency.

Exit:

  • no unresolved critical API/UX mismatch

R5 Quality Gate Upgrade (Day 6)

  • Ensure CI/release gate includes test execution (not build-only).
  • Lock release rehearsal checklist.

Exit:

  • gate policy documented
  • CI and release gates green on dry run

R6 Fix Sprint (Day 7-9)

  • Land fixes from R2-R5 by severity.

Exit:

  • P0 = 0
  • P1 reduced to explicit accepted risks only

R7 Docs & Messaging Sync (Day 9-10)

  • Sync README/docs/standards/reference to code truth.
  • Add release assets (CHANGELOG, notes, support/security policy).

Exit:

  • sampled docs have 0 factual mismatch
  • release assets ready

R8 Release Rehearsal (Day 10)

  • End-to-end rehearsal: build, install, smoke, mcp handshake, core workflows.

Exit:

  • rehearsal report complete
  • go/no-go decision recorded

R9 Tag and Publish RC19 (Day 11)

  • bump version
  • tag + publish TestPyPI
  • publish release notes

Exit:

  • install/upgrade path verified
  • rollback path documented

5. Required Artifacts

  • docs/release/RC19_OWNER_MAP.md
  • docs/release/rc19_file_matrix.csv
  • docs/release/RC19_FINDINGS_REGISTER.md (instantiated per real findings)
  • docs/release/RC19_GATES.md
  • docs/release/RC19_EXECUTION_CHECKLIST.md
  • docs/release/rc19_contract_gap.md
  • docs/release/rc19_core_findings.md
  • docs/release/rc19_port_parity.md
  • docs/release/rc19_strategic_review.md
  • docs/release/rc19_rehearsal_report.md

6. Severity Policy

  • P0: correctness/data-loss/security or release blocker
  • P1: major behavior drift or operational risk
  • P2: polish/maintainability

Release rule:

  • rc19: requires P0=0
  • GA: requires P0=0 and no unowned P1

7. GA Readiness Gate (post-rc19)

0.4.0 is allowed only when:

  • rc19 soak passes
  • protocol/docs/CLI/MCP/Web terminology converged
  • release pipeline and rollback are reproducible